How will the expansion of the charging infrastructure in Berlin proceed?

The expansion of the charging infrastructure is being implemented in two phases:

In the supply-oriented phase, 359 charging points for electronic vehicles were installed in the public and semi-public areas within 169 search spaces.

There are 159 charging stations in public spaces, as well as six charging stations and three wall boxes in semi-public spaces. In addition, eleven streetlight charging stations and six fast charging stations were installed.

We documented and certified 850 locations to establish the charging infrastructure in the first phase. We queried grid provider Stromnetz Berlin to ascertain the suitability of 550 locations for connection to the low-voltage grid. Around one-third of these were introduced into the approval procedure in coordination with the districts.

In addition to the supply-oriented phase, the demand-oriented phase (Phase II) started in January 2016, rolling out the expansion according to established demand.

To date, one streetlight charging point and three regular charging points were put into operation.